Ireland’s RESS 6 Awards 1,367 MW of Solar at EUR 0.10242 per kWh
Where the market stands
According to the Global Solar Industry Research Institute under SolarPanelsLink, Irish grid operator EirGrid has published provisional results for the sixth onshore renewable electricity support scheme auction, and solar again dominated with 22 projects and 1,367.24 MW provisionally approved.
Onshore wind won only 6 projects and 188.05 MW, so solar took about 7.3 times the wind volume.
The weighted average solar bid was EUR 0.10242 per kWh, about USD 0.1121.
Compared with the 860 MW provisionally approved in RESS 5 in September 2025, solar volumes rose about 59% in a year.
Total deemed energy in RESS 6 was 1,894.04 GWh, of which solar was 1,317.48 GWh; a further 977.67 GWh of solar did not receive provisional approval. Four projects failed to qualify, all solar, and 13 withdrew, six solar and seven wind.
Most approved solar projects are in eastern Ireland near County Meath, close to the Dublin load centre and stronger grid.
Developers Soleire Renewables and Harmony Solar were the most active by capacity. Solar Ireland chief executive Ronan Power said more solar could have been approved if unsuccessful projects were counted, and that Ireland had in effect said no to an additional 1 GW.
He noted the results are provisional and that the priority is converting awards into built projects, with financing, grid connection and construction deciding the outcome.
RESS 6 results are due to be finalised on 9 December, with award letters planned for 11 January 2027.
Ireland has more than 3 GW of solar and expects to exceed 3.3 GW by year end, against an 8 GW target for 2030, leaving about 4.7 GW to build; this auction's 1,367 MW is about 30% of that gap.
Source: SolarPanelsLink
Unlock the Ireland intelligence briefing
Get tender calendars, tariff benchmarks, local-content rules and the project pipeline behind the headline numbers.
- Procurement calendar and upcoming tenders
- Tariff and PPA benchmark ranges
- Local content and permitting rules
- Pipeline and offtake watch items