Inner Mongolia’s 2 GW Alxa-to-Wuhai Renewable Project Connects to the Grid
The 2 GW Alxa-to-Wuhai regional renewable project in Inner Mongolia, including 1.7 GW of solar, 300 MW of wind and 300 MW/600 MWh of storage, achieved first grid connec…
CGN has built 337.5 MW of wind and 100 MW of solar in Shilou, Shanxi, generating about 700 GWh a year, within a planned 937.5 MW wind-solar-hydrogen-storage base costing about CNY 5.42 billion, with roughly 500 MW still to build.
According to SolarPanelsLink, Shilou county in Shanxi held a project inspection on 24 and 25 November covering 19 projects, disclosing progress on CGN's wind-solar programme and the Maoyuan 100 MW standalone hybrid storage project.
CGN has built 337.5 MW of wind and 100 MW of solar in Shilou, generating about 700 GWh a year. It plans a wind-solar-hydrogen-storage demonstration base with 937.5 MW of cumulative capacity and about CNY 5.42 billion of investment, its largest county-level project in Shanxi.
The 437.5 MW already built is about 46.7% of the plan, leaving roughly 500 MW to build. At 437.5 MW for 700 GWh, combined utilisation is about 1,600 hours, above a solar-only plant. Investment of CNY 5.42 billion on 937.5 MW implies about CNY 5.78 per watt.
Create a free account to read a longer preview. Full project reports and procurement detail are available to Pro and Business members.
Unlock procurement structure, tariff benchmarks, delivery status and live supply opportunities for this project.
The 2 GW Alxa-to-Wuhai regional renewable project in Inner Mongolia, including 1.7 GW of solar, 300 MW of wind and 300 MW/600 MWh of storage, achieved first grid connec…
The first 700 MW solar phase of CNNC Huaneng’s 1.6 GW Jinta clean energy base in Gansu has connected to the grid, the first Gansu project in China’s third batch of larg…
Sinohydro Bureau 9 has completed acceptance of 17 solar projects totalling 1,135 MW across Jinghong, Menghai and Mengla in Xishuangbanna, Yunnan, including five 220 kV …