Avantus Signs 20-Year PPAs with PG&E for Buttonbush 1A and 1B
Avantus has signed 20-year PPAs with PG&E for the first two phases of its Buttonbush solar centre in Kern County, California, covering 800 MW of solar and 3,200 MWh of …
Inox Solar Americas has moved its 3 GW solar cell factory in Greenville, North Carolina, into equipment installation, with commercial production scheduled for the second quarter of 2027.
According to the Global Solar Industry Research Institute under PV Business News, Inox Solar Americas LLC has moved its 3 GW solar cell manufacturing plant in Greenville, North Carolina, into the equipment installation phase, with commercial production on schedule to begin in the second quarter of 2027.
The plant covers 515,460 square feet and serves as the company's US manufacturing base. Once operational, it will supply locally made monocrystalline cells directly to Inox Solar Americas' own module assembly operations, while producing the Galaxion cell architecture together with Gamma-series monofacial and Vega-series bifacial modules.
The Greenville project builds on Inox Clean Energy's acquisition of Boviet Solar's US manufacturing assets, a deal that included an established 3 GW module line and a planned cell expansion. By using existing infrastructure rather than starting from scratch, the company avoided the greenfield timelines that have held back domestic manufacturing in the United States.
US module capacity has reached 75–80 GWdc, while cell capacity stands at only around 20 GWdc, wafer capacity at about 3 GWdc and polysilicon at roughly 10 GWdc. Module capacity is therefore nearly four times cell capacity and about 25 times wafer capacity. This "strong assembly, weak upstream" structure mirrors Europe, where HoloSolis' planned 5 GW plant is likewise positioned as a module assembly site that will initially rely on externally supplied cells.
Across the wider supply chain, US manufacturing is entering a heavy-capex phase. Tesla is advancing a vertically integrated plant near Houston, Texas, at an investment scale of around US$10 billion, covering the full chain from ingot and wafer to cell and module, with completion targeted for 2028 and operation in the first quarter of 2029 at a capacity goal in the 100 GW class. SpaceX has already signed a turnkey heterojunction cell line contract with Germany's SINGULUS, with the first line order worth more than €60 million and delivery planned for the first half of 2027.
Source: PV Business News
Avantus has signed 20-year PPAs with PG&E for the first two phases of its Buttonbush solar centre in Kern County, California, covering 800 MW of solar and 3,200 MWh of …
Duke Energy Florida has filed regulatory applications for four new solar facilities totalling 300 MW in Orange and Sumter counties, a portfolio expected to save custome…