🇲🇾Malaysia Asia Pacific Construction

MN Holdings Wins RM1.12 Billion EPCC for 400 MWac LSS Project in Kemaman

400 MW Utility-scale solar Updated today
Public summary

MN Holdings subsidiary MNUESB has won a RM1.12 billion fixed-price EPCC contract for two large-scale solar plants totalling 400 MWac in Kemaman, Terengganu, under Malaysia's LSS PETRA 5+ scheme, with completion targeted for 30 June 2028.

Project report

Updated 20 Nov 2026

According to the Global Solar Industry Research Institute under SolarPanelsLink, MN Utilities Engineering Sdn Bhd (MNUESB), a wholly owned subsidiary of MN Holdings Bhd, has won a fixed-price engineering, procurement, construction and commissioning (EPCC) contract worth RM1.12 billion. The company says it is its largest contract to date and its first entry into the large-scale solar (LSS) segment.

In a filing with Bursa Malaysia, MN Holdings said the project was awarded by RE Kemaman Sdn Bhd and RE Kemaman II Sdn Bhd under the LSS PETRA 5+ scheme.

The contract covers integrated design, engineering, procurement, construction, testing and commissioning of two LSS solar facilities in Kemaman, Terengganu. The two facilities have contracted export capacities of 250 MWac and 150 MWac respectively, totalling 400 MWac. The turnkey scope also includes associated grid connection facilities and grid works designed for a 25-year life.

According to SolarPanelsLink, a recent landmark in the Malaysian market was Northern Solar Holdings Berhad's two solar-plus-storage contracts under the Corporate Renewable Energy Supply Scheme (CRESS), totalling 189 MWac and supplying two data centres with close to 500 million kWh of annual demand. By comparison, this 400 MWac contract is larger than those two combined, and it comes through the government's LSS PETRA 5+ tender channel rather than the CRESS corporate direct-supply route — two separate systems.

According to SolarPanelsLink, MNUESB will act as project leader in a three-party consortium that includes China Railway 11th Bureau Group Electrical Engineering Co Ltd (CRCC11GEE) and DB Energy Sdn Bhd. Under the consortium arrangement, MNUESB holds 66% of the responsibilities and benefits, while CRCC11GEE and DB Energy each hold 17%.

According to SolarPanelsLink, work will start after receipt of the Notice to Proceed and is scheduled for completion by 30 June 2028 — an execution period of a little over a year and a half from today.

MN Holdings management said the award builds on the group's track record in underground utilities and high-voltage substation works, allowing it to participate directly in Malaysia's energy transition.

Looking ahead, the group plans to pursue more renewable energy opportunities and explore strategic equity investments to generate recurring income. Moving from EPCC contracting to owning and operating assets changes the revenue structure: contracting is one-off income, while equity holdings provide long-term cash flow.

According to SolarPanelsLink, MN Holdings' core power infrastructure division remains well positioned to benefit from rising data centre electricity demand, Tenaga Nasional Bhd's RM42.8 billion RP4 capital expenditure plan and the RM15 billion national grid investment under the 2027 budget.

Source: SolarPanelsLink