Frontier Energy has started construction on phase one of its Waroona project in Western Australia, combining 132 MW of solar with 81.5 MW of storage over 6.9 hours in a DC-coupled design, with first generation planned for 2028.
According to SolarPanelsLink, Perth-based clean energy developer Frontier Energy has started construction on phase one of its flagship Waroona Renewable Energy Project in south-western Western Australia, with first generation planned for 2028.
Phase one, about 120 km south of Perth, includes a 132 MW solar facility and an 81.5 MW battery system with 6.9 hours of duration. Pairing 132 MW of solar with 6.9 hours of storage is longer than the usual proportional storage ratio: the configuration is designed to move daytime generation into higher-priced periods rather than simply exporting energy to the grid.
The project uses a DC-coupled design, capturing solar during the day and discharging into the grid at high-value demand periods. DC coupling connects storage directly to the solar DC bus, cutting intermediate AC/DC conversion stages — a configuration tailored to intraday energy shifting.
Frontier chief executive Adam Kiley said the project will connect to Western Australia's main grid, the South West Interconnected System (SWIS), through the nearby 330 kV Landwehr terminal station, and will make a material contribution to the state's clean energy transition, with phase one expected to replace one third of the output of the coal-fired Collie plant scheduled to close in 2027.
He said that once generation begins in 2028, Waroona will be the largest solar and battery hybrid facility connected to the SWIS and an important part of Western Australia's target of 75% renewable energy by 2031. He also said the company intends to develop Waroona into a multi-stage renewable energy hub.
Kiley said phase one is only the beginning, with Frontier aiming to build Waroona into a major renewable hub in the south-west interior, bringing much-needed new generation to a region supported by coal for more than 60 years.
Beyond phase one, Frontier plans to scale up substantially, with a longer-term ambition of about 1 GW of solar generation and 660 MW of battery storage by 2031. Phase two has development approval for about 120 MW of solar and 80 MW of battery storage.
From 132 MW in phase one to a 1 GW target for 2031, nearly 900 MW of further solar capacity remains to be released.
According to SolarPanelsLink, local contractor Monford Group holds the fixed-price engineering, procurement and construction contract for phase one, covering construction and commissioning of the integrated solar and storage facility. Chinese manufacturer LONGi was selected to supply modules, Trina Storage will provide the battery system, Nextpower the trackers and SMA Australia the inverters. Of the five core suppliers, modules, storage and trackers all went to Chinese companies.
Source: SolarPanelsLink