🇨🇳China Asia Pacific Tender Storage

Bengbu Development Zone Tenders 129.7 MWp Green Energy Microgrid EPCO

130 MW C&I rooftop Updated today
Public summary

Bengbu Economic Development Zone has tendered an EPCO contract for a park-wide green energy project combining 129.7 MWp of PV, 100 MW/200 MWh of shared user-side storage, charging infrastructure and a microgrid platform, with total investment of RMB 973.5 million.

Project report

Updated 20 Nov 2026

According to SolarPanelsLink, a tender announcement for the Bengbu Economic Development Zone integrated green energy (smart microgrid) EPCO project was published on 19 November.

Total investment is RMB 973.53 million (about RMB 974 million), making it the largest park-level integrated green energy project in Anhui in recent months and a full-scale deployment of the "solar-storage-charging plus microgrid plus zero-carbon park" model in a county-level development zone.

The tendering entity and project owner are both Bengbu Hongjiang Energy Technology Development Co., Ltd. Funding is 100% state-owned, the tender is open and uses a separation of evaluation and award, with a comprehensive evaluation method and a single lot.

The site is Bengbu Economic Development Zone, covering the whole zone and its administered areas, including the Sensor Valley industrial park, Lingang industrial park, University Science and Technology Park and the 214 Institute site.

The scope includes about 129.7 MWp of new PV, three energy stations, 10 kV lines, an all-electric wharf with 25 shore-power boxes, 220 EV chargers, 20 small user-side storage units of 500 kW/1,044 kWh, a shared user-side storage system of 100 MW/200 MWh, a 1,440 kW heavy-truck battery-swap station, and an integrated energy management platform with supporting control centre. The tender excludes the 110 kV substation and lines and the 35 kV distribution works within the feasibility study scope.

The project is implemented in two phases. Phase 1, with total investment of RMB 436.05 million, covers 55 MWp of rooftop PV, a 20 MW/40 MWh storage system, 20 integrated solar-storage-charging stations (10 MWp, 20.88 MWh and 120 chargers), one 1,120 kW heavy-truck charging station with space reserved for expansion, a central heating and cooling energy station at Sensor Valley, an integrated energy management platform, supporting 10 kV distribution lines and a control centre. Phase 2, at RMB 537.48 million, covers 64.7 MWp of PV, two energy stations, 10 kV lines, an all-electric wharf with 25 shore-power boxes, 100 EV chargers, expansion of the heavy-truck charging station (adding 320 kW units) and an 80 MW/160 MWh shared user-side storage system.

Each sub-project has a 150-day construction period — 30 days for design and 120 days for construction — excluding grid-connection acceptance and commissioning.

From publication on 19 November to bid opening on 10 December, the bidding window is only three weeks.

Source: SolarPanelsLink