Jilin Da'an 900 MW Solar Block in the 'Jilin Power to Beijing' Programme

900 MW Utility-scale solar Updated today
Public summary

The Da'an government work report discloses a 900 MW solar block within the 'Jilin Power to Beijing' programme, backed by RMB 7 billion and scheduled for completion by the end of 2029, with construction running from 2026.

Project report

Updated 20 Nov 2026

According to SolarPanelsLink, the new energy plan disclosed in the Da'an municipal government work report shows that the five construction blocks of the "Jilin Power to Beijing" programme include a solar block: RMB 7 billion of investment for 900 MW of PV, scheduled to be completed and put into use by the end of 2029.

RMB 7 billion against 900 MW works out to about RMB 7.78 per watt, which suggests the solar block covers not only the PV plant itself but likely also collection, boosting and transmission infrastructure.

"Jilin Power to Beijing" targets cross-regional power delivery, and the green power from its supporting solar plants ultimately serves the Beijing load centre. Neighbouring Inner Mongolia has already established this model: four point-to-grid lines — including Daihai–Shunyi and Jinglong–Fangshan — deliver green power to Beijing. By the end of 2025 the region had built 5.5 GW of new energy for this purpose, sending more than 15 TWh of green power to Beijing each year, saving around 5 million tonnes of standard coal and cutting about 12 million tonnes of CO2. A further 4 GW is expected to be added by the end of 2027, taking annual green power deliveries to Beijing to 24 TWh. Inner Mongolia has built multiple 1,000 kV AC ultra-high-voltage corridors and 500 kV point-to-grid and grid-to-grid links to Beijing, with total transmission capacity of around 24 GW. Jilin and Inner Mongolia sit on the same north-east to north China power corridor, and "Jilin Power to Beijing" follows a similar cross-regional route.

Construction runs from 2026 to the end of 2029 — roughly three years from today, much slower than the typical centralised PV schedule of construction in one year and grid connection the next.

Cross-regional delivery projects usually have to be matched to the receiving grid's absorption capacity and to the progress of transmission corridors; bringing supporting generation online before or after the corridor is available wastes resources.

The same report also sets out 2027 plans: start construction on new projects including TBEA's 200 MW and Yaoyang's 50 MW, adding 1.08 GW of new energy capacity and advancing thermal, wind, solar and grid as four integrated blocks. It does not specify whether the TBEA and Yaoyang projects are solar or wind.