Jilin Da'an 900 MW Solar Block in the 'Jilin Power to Beijing' Programme
The Da'an government work report discloses a 900 MW solar block within the 'Jilin Power to Beijing' programme, backed by RMB 7 billion and scheduled for completion by t…
The 100,000 t/y liquid-sunshine methanol demonstration in Wushen Banner, Ordos pairs 400 MW of PV and 226 MW of wind with green hydrogen and CO2-to-methanol synthesis; investment is RMB 4.9 billion and full commissioning is targeted for May 2027.
According to SolarPanelsLink, Ordos, a national energy base, is implementing a "green hydrogen plus" programme that links production, storage, transmission and use, and two hydrogen-linked industrial projects are advancing in Otog Front Banner and Wushen Banner.
The first is the Shenzhen Energy Otog Front Banner integrated wind-solar hydrogen-to-green-ammonia project, built around green power for hydrogen and green hydrogen for ammonia. It includes 500 MW of wind, hydrogen production, storage and ammonia synthesis facilities, and a planned 5 GW PV direct-current off-grid hydrogen demonstration, creating an integrated chain from renewable generation to green chemical products.
According to project site manager Luo Yifan, the wind farm is already grid-connected and the hydrogen plant is in production, with system testing and optimisation under way; the ammonia unit is being installed and prepared for commissioning, with completion targeted by the end of the year. The main hydrogen system is designed for 48,000 standard cubic metres per hour, and the ammonia plant for 150,000 tonnes a year.
At 48,000 cubic metres an hour, daily hydrogen output is about 1.152 million cubic metres. At roughly 660 cubic metres of hydrogen per tonne of ammonia, 150,000 tonnes a year requires about 99 million cubic metres, broadly matching the hydrogen capacity. The project links green energy with chemical production: green power electrolysis makes the feedstock green, while the hydrogen-to-ammonia chain converts electricity into a chemical product that is easier to store and transport, widening renewable absorption and keeping more value locally.
The 5 GW PV direct-current off-grid hydrogen demonstration bypasses the conventional inverter-grid-utility route by feeding DC power straight to the electrolysers, avoiding conversion losses from inversion and transformation. The route has so far been limited to kilowatt-scale trials; a 5 GW demonstration would be frontier work for the industry. The 500 MW of wind provides steady baseload supply.
Luo said the region's wind and solar resources underpin green hydrogen, its established energy and chemical industry creates room for green hydrogen and ammonia applications and supply chains, and mature park infrastructure supports construction and operation. The project turns local resources into local industrial advantage.
Meanwhile, the China Coal Ordos Energy and Chemical 100,000 t/y liquid-sunshine methanol demonstration in the Tuke industrial park of Wushen Banner is progressing. It is the world's first industrial-scale liquid-sunshine project, with total investment of RMB 4.9 billion and a green power system of 400 MW of PV and 226 MW of wind. Green hydrogen from electrolysis is combined with CO2 to make methanol, completing a "wind-solar green power, green hydrogen, carbon cycle" chain.
The 400 MW of PV plus 226 MW of wind totals 626 MW, implying about RMB 7.83 per watt of investment — higher than conventional wind-solar plants because, beyond generation, the project includes electrolysis, CO2 capture and methanol synthesis.
Liu Liqiang, deputy general manager of the new energy branch of China Coal Ordos Energy and Chemical, said turbine installation is under way on the generation side, the chemical side has reached mechanical completion, system commissioning is expected in March 2027, and the full process should be connected by the end of May. Once operating, the plant will produce 100,000 tonnes of green methanol a year and consume 150,000 tonnes of CO2 from chemical tail gas.
The green-hydrogen-to-methanol model uses CO2 purified from chemical tail gas with green hydrogen; at 150,000 tonnes of CO2 and 100,000 tonnes of methanol, each tonne of methanol absorbs about 1.5 tonnes of CO2, consistent with the stoichiometry of liquid-sunshine synthesis. The project is a flagship for Ordos' zero-carbon industrial model and a new path for greening traditional coal chemicals.
Source: SolarPanelsLink
The Da'an government work report discloses a 900 MW solar block within the 'Jilin Power to Beijing' programme, backed by RMB 7 billion and scheduled for completion by t…
Hebei has approved land conversion for the 300 MW Yunzhou solar plant, part of Zhangjiakou Power Plant's million-kilowatt new energy base, covering 1.7038 hectares of c…
Bengbu Economic Development Zone has tendered an EPCO contract for a park-wide green energy project combining 129.7 MWp of PV, 100 MW/200 MWh of shared user-side storag…